Root Cause Analysis of Project Delay in BGC-TEG Project
##plugins.themes.bootstrap3.article.main##
PT WEI is a company that the main business as fabricator contractor for oil and gas and renewable energy industry located at Batam, Indonesia, they have operate for more than 15 years. The company produce types of facilities such as Process Packages module, FPSO (Floating Production Storage and Offloading) Topside Modules, E-house module and Sub-Station packages for client from all over world. The problem on this research is the delivery delay issue during execution of the BGC-TEG project. the project that have scope of EPC (Engineering Procurement and Construction) contract for delivery process module include mechanical equipment, piping and accessories for client at middle east, the delivery project delay is 21 months from original contract 11 months. The research to determine main factor that contribute to the delay by quantitative method, to gain information and identify alternative for improvement action. The primary data gathered from interview with some person in charge team member of the project. The secondary data gain from internal company document, project record and report, and project repository data base. Study literature of some similar case of project delay from various papers and articles reviewed. Fishbone diagram as analysis method with framework based on PMBOK by Project Management Institute to gain the root cause factors and propose solution alternative action to prevent same issue happen on future.
Downloads
References
-
Ahmed, T, Delay in construction project (2015). The American University of Iraq, Sulaimani.
Google Scholar
1
-
Al-Adwani, M.M., Mollasalehi, S. & Fleming, A.J. (2018). A Study of root causes of delays in the public-sector construction project in Kuwait, University of Salford Manchester.
Google Scholar
2
-
Fanousse, M.I. (2017). Cause of Delay in construction Project in Oil and Gas Construction Industry, The British University in Dubai.
Google Scholar
3
-
Hwang B.G, Leong, L.P. (2013). Comparison of schedule delay and causal factors between traditional and green construction projects. Technological and Economic Development of Economy, 19(2), 310-330.
Google Scholar
4
-
Hamzah, N., Khoiry, M.A., Arshad, I., Tawil, N.M., & Che Ani, A.I.(2011), Cause of Construction Delay – Theoritical Famework, The National University of Malaysia.
Google Scholar
5
-
Paray, W.A, Kumar, C. (2020). Delay Analysis in construction project; IRJET (07).
Google Scholar
6
-
Project Management Institute. A guide to the Project Management Body of Knowledge (PMBOK 2017) 6th ed.
Google Scholar
7
-
Seno, G.W., Firman, A.S. (2018). Analysis of critical factors causing project closeout delay at PT Gas Mandiri, IJBA. 7(2), 1-3.
Google Scholar
8
-
Trauner Jr, T.J. Book (Construction Delay: Understanding them clearly, analyzing them correctly) 2nd edition (2009).
Google Scholar
9
-
Wealleans, D. (2017). The organizational Measurement Manual, Taylor & Francis.
Google Scholar
10
-
Zarei, B, Sharifi H, & Chagouee Y. (2017). Delay Cause Analysis in complex construction project; a semantic Network Analysis Approach, University of Liverpool.
Google Scholar
11
Most read articles by the same author(s)
-
Rahardian A. Saputra,
Gatot Yudoko,
Aries F. Firman,
Proposed Strategy of Heavy Equipment Overhaul: Case Study of a Coal Mining Contractor in Indonesia , European Journal of Business and Management Research: Vol. 8 No. 4 (2023) -
Desi Aresa Mahdi,
Gatot Yudoko,
Agung Wicaksono,
Debottlenecking The Complexities of Stakeholder Management in Indonesia Offshore Platform Decommissioning , European Journal of Business and Management Research: Vol. 8 No. 5 (2023) -
Khusnah Arthamin Nikmatul,
Gatot Yudoko,
Aries F. Firman,
Improvement of Turnaround Maintenance Project Execution Through Long-Term Specific Contracting Strategy (A Case Study: Gas Processing Plant in Indonesia) , European Journal of Business and Management Research: Vol. 8 No. 4 (2023)