RAM Analysis at Gas Turbine Power Plant with Six Sigma Method
##plugins.themes.bootstrap3.article.main##
The goal of this study is to identify breakdown that has an impact on the gas turbine engine's RAM and Six Sigma level in order to assess how well the gas turbine engine performance through the value of RAM (Reliability, Availability, and Maintainability) and Six Sigma. By gathering, compiling, categorizing, and conducting an analysis of data and information on the utilization of gas turbine engines, based on actual data and information, the descriptive analysis method is used to reveal the availability and performance of gas turbine engines. The findings of the RAM and Six Sigma level are examined utilizing the Pareto chart to identify the most impacted breakdown, the Fishbone diagram for root cause analysis, and the five why analysis approach for improvement suggestions. According to research findings, control system failure, VGV system failure, and load distribution problem have an impact on the RAM and Six Sigma level of two gas turbines. The Root cause of the issue is due to a number of factors, including mostly due to technical issues of unreliable old control system and VGV system design, an incorrect maintenance schedule implementation, an incompetent and ignorant of operator or technician to gas turbine engines.
Downloads
References
-
Samat, H. A., Kamaruddin, S., & Azid, I. A. (2012). Integration of overall equipment effectiveness (OEE) and reliability methods for measuring machine effectiveness. South African Journal of Industrial Engineering, 23(1), 92-113.
Google Scholar
1
-
Choudhary, D., Tripathi, M., & Shankar, R. (2019). Reliability, availability and maintainability analysis of a cement plant: a case study. International Journal of Quality & Reliability Management, 36(3), 298-313.
Google Scholar
2
-
Ebeling, C. (2000). An Introduction to Reliability and Maintainability Engineering, Tata McGraw-Hill.
Google Scholar
3
-
Kumar, V., Verma, P., & Mut Hukumaar, V. (2018, March). The performances of process capability indicators in the Six-Sigma competitiveness levels. In Proceedings of the International Conference on Industrial Engineering and Operations Management (pp. 1945-1951).
Google Scholar
4
-
Kurniawan, F. (2013). Engineering and application industrial maintenance management. Graha knowledge. Yogyakarta.
Google Scholar
5
-
Nusraningrum, D., & Gana-Senjaya, E. (2019). Over all Equipment Effectiveness (OEE) Measurement Analysis on Gas Power Plant with Analysis of Six Big Losses. International Journal of Business Marketing and Management (IJBMM), 4(11), 19-27.
Google Scholar
6
-
PRAESITA, I., Alhilman, J., & Nopendri, N. (2016). Performance Assessment Based on Reliability on Continuous Casting Machine 3 (CCM 3) Pt Krakatau Steel (Persero) Tbk Using Reliability Availability Maintainability and Cost of Unreliability Methods. JRSI Journal of System and Industrial Engineering, 3(04), 1-6.
Google Scholar
7
-
Rahayu, N. A., & Santoso, S. (2021). Implementation of six sigma to minimize reject gusset difference and fold in the blowing process. European Journal of Business and Management Research, 6(4), 1-6.
Google Scholar
8
-
Warinah, D. N., & Nusraningrum, D. (2019). Application of Six Sigma (Dmaic) Method to Reduce Defect Amount in Assembly Process A Case Study PT. XYZ. International Humanities and Applied Sciences Journal (Ihasj), 2(3), 58-71.
Google Scholar
9
Most read articles by the same author(s)
-
Dewi Nusraningrum,
The Sustainability of Competitive Strategy in the Tourism Services Industry , European Journal of Business and Management Research: Vol. 7 No. 4 (2022) -
Pristiyani Solikhah,
Dewi Nusraningrum,
Increasing Production Capacity of Oil Country Tubular Goods Pipe Using Oee Methods , European Journal of Business and Management Research: Vol. 7 No. 5 (2022) -
Teuku Riza Syahrial,
Dewi Nusraningrum,
Improving Performance and Electricity Production with the Overall Equipment Effectiveness Method as the Basis for the Proposed Application of the Total Productive Maintenance Concept on the PLTS Equipment System at Soekarno-Hatta Airport , European Journal of Business and Management Research: Vol. 7 No. 4 (2022) -
Ryan Adismar,
Dewi Nusraningrum,
Construction Process Business Model Strategy to Fulfil the Working Contract at PT Uniteda Arkato , European Journal of Business and Management Research: Vol. 7 No. 4 (2022)